What does a fill stake indicate?

  1. The area needs to be excavated

  2. The area is at the desired grade

  3. The ground must be raised with additional material

  4. The ground is too high and needs to be lowered

The correct answer is: The ground must be raised with additional material

A fill stake is a physical marker used in construction and surveying to indicate that the ground in a specific area needs to be raised, usually with additional materials such as soil or gravel. This is essential for ensuring that the area reaches the desired elevation or grade for planned construction or roadway design. The fill stake provides guidance to contractors and construction teams on where they need to add material to achieve proper levels, which is critical for drainage, stability, and overall project specifications. By identifying where the fill is required, it helps in accurately managing the earth-moving operations, leading to more efficient use of resources and time. The other choices do not accurately reflect the function of a fill stake; for instance, stating that an area requires excavation misrepresents the fill stake's purpose, as it indicates the need for raising the ground rather than lowering it.